Ericsson 3G/4G – Adding New Sectors to Existing Sites (MOPs, Procedures and Scripts Needed)

Ericsson 3G/4G – Adding New Sectors to Existing Sites (MOPs, Procedures and Scripts Needed)

Hello TelecomHall Community,

I am looking for technical support from engineers with experience in Ericsson RAN operations, maintenance and network integration.

I have recently received an assignment to add new sectors to existing Ericsson 3G and 4G sites.

Network environment:

  • 3G: Ericsson RBS 6000 / RNC.

  • 4G: Ericsson RBS 6000 / eNodeB.

  • Baseband equipment: DUW, DUS, BB5216, BB6630 and potentially other configurations depending on the site.

  • Some sites may use existing baseband capacity, while others may require additional baseband hardware.

I would appreciate any technical documentation, practical experience, procedures or automation scripts that could help me perform this activity.

1. Hardware installation and preparation

  • Hardware requirements for adding new sectors.

  • RRU, antenna, RET and baseband considerations.

  • Hardware connectivity and cabling.

  • Baseband capacity checks and hardware expansion.

  • DUW/DUS/BB5216/BB6630 configuration considerations.

2. Ericsson 3G – RBS 6000 / RNC

  • Step-by-step procedure for adding a new sector to an existing NodeB.

  • Required NodeB and RNC configuration changes.

  • Radio equipment and cell configuration.

  • Relevant Moshell/AMOS commands and scripts.

  • Integration and commissioning procedures.

3. Ericsson 4G – RBS 6000 / eNodeB

  • Step-by-step procedure for adding a new sector to an existing eNodeB.

  • Required configuration changes (cells, sectors, radio equipment, etc.).

  • Baseband and radio configuration.

  • Relevant Moshell/AMOS commands and scripts.

  • Integration and commissioning procedures.

4. Automation scripts
I am particularly interested in:

  • Scripts for adding 3G sectors.

  • Scripts for adding 4G sectors.

  • Configuration and integration automation.

  • Pre-check and post-check scripts.

  • Commands to collect and compare existing site configurations.

5. MOP, verification and rollback

  • Complete MOP examples.

  • Pre-integration checks and prerequisites.

  • Post-integration verification.

  • Alarm checks and troubleshooting.

  • Cell availability and operational status.

  • Rollback procedures in case of failure.

If anyone has already performed similar activities on Ericsson networks, I would greatly appreciate sharing your experience, recommendations, documentation, MOPs or scripts.

Practical examples are especially welcome.

Thank you in advance for your support.

Best regards.

Hi, @sofiane1, there are a lot to discuss for one topic. Must have starter pack is to install ELEX with libraries and to read help topics in amos.

Hi, thank you for your advice.

I understand that there is a lot to cover in this topic. I will take your recommendation into consideration and start by installing ELEX with the required libraries and exploring the AMOS help topics.

However, if possible, could you please guide me through the most important steps for adding a new sector to an existing Ericsson 3G/4G site?

Even a basic step-by-step overview of the process, including the main configuration changes, essential AMOS commands, and post-integration checks, would be very helpful.

I would really appreciate your guidance and experience.

Thanks in advance!

@sofiane1
Connect to node with amos

amos <NODENAME>
# or
amos <IP>

load objects

lt all

enter simulate mode

u+s

simulate deletion of required objects

rdel EUtranCellFDD=<CELLNAME>

exit sim mode

u-

modify undo file with your new parameters

l vi /path/to/undofile.mos

execute modified undo file

run /path/to/undofile.mos

new cell will be created.
To do more experiments save mo dump

amos <NODENAME>
dcgk

this will retun something like mo dump saved to /path/to/modump
after connect to this dump

amos /path/to/modump

now you try any commands without interruptions on service.
Post checks

# alarms
alt
# states
st cell
st sect
st mme
sts

Hi. Many thanks i will try it.